Work Scheduled for Monday 5/15/17

Work Scheduled for Friday 5/12/17.

Work scheduled for Wednesday 5/11/17

Work Scheduled for Wednesday 5/10/17

Work Scheduled for Tuesday 5/9/17

Work Scheduled for Friday 5/5/17

Work Scehduled for Thursday 5/4/17 - Pavement Removal on Alley #5. Concrete pour on Alley #2. No work on Alley #4 due to wet conditions.

Project Update 5/1/17 - No work for Monday May 1st, due to weather conditions.

Concrete Pavement Pour Alley #1 / Excavation Alley #2 for Tuesday April 18, 2017

No work on Alley #1 and Alley #2 for Thursday April 13, 2017 due to weather.

No work on Alley #1 and Alley #2 for Friday April 7, 2017 due to wet soil conditions. Work to resume on Monday April 10,2017.

No work on Alley #1 and Alley #2 for Wednesday April 6, 2016 due to weather.

No work on Alley #1 and Alley #2 for Wednesday April 5, 2016 due to weather.

No work on Alley #1 and Alley #2 for Monday April 3, 2017 due to weather.

Project Update: Alley #1 - Pavement Removal 03-31-2017, Alley #2 - Saw Cutting April 3rd, 2017